Five jobs are waiting to be executed. their expected (running time, priority, deadline) are as follows
( 10, 5, 13), ( 15, 9, 17 ), ( 18, 12, 20 ), ( 15, 7, 23 ), ( 15, 7, 17 )
J1 J2 J3 J4 J5
Time 10 15 18 15 15
Priority 5 9 12 7 7
Deadline 13 17 20 23 17

a. Mean response time?
b. Mean weighted response time?
c. Minimize maximum lateness?
 