TIMELINE: Cabagan-Sta. Maria Bridge in Isabela province
2014: The Department of Public Works and Highways (DPWH) awarded a PHP 412.9 million contract to R.D. Interior Junior Construction for the construction of a 720-lineal meter bridge across the Cagayan River, connecting the towns of Cabagan and Sta. Maria.
2015: President Benigno S. Aquino III highlighted the ongoing construction of the Cabagan-Sta. Maria Bridge as a significant infrastructure project aimed at connecting Isabela to the Cordillera Administrative Region.
2017: Construction of the new bridge commenced with an initial budget of P639.6 million.
2018: DPWH Regional Director Engr. Melanio Briosos reported that due to additional expansions, the project's cost increased to P1 billion, delaying completion to 2019.
2023: The DPWH engaged CFC Fiber Construction Corporation for retrofitting and strengthening works to ensure the bridge's durability.
2024: The Provincial Government of Isabela allocated PHP 36,000,000 for the Sta. Maria Bridge Lighting Project, aiming to enhance safety features of the bridge.
September 2024: The bridge was opened to light vehicles, with plans to accommodate all vehicles by the end of the month.
February 27, 2025: Tragically, the bridge collapsed this evening. Initial reports suggest that an overloaded truck may have contributed to the structural failure.