Ans
One worker take average 40 minutes an order in paper work .
The total time any worker gets is 9 to 6 o evening from which the person gets 1 hour off for lunch and 15% of the remaining time loses for other thing . Hence the total time left for the workers in minutes = 7*60 minutes-1*60 minutes(lunch)= 360 minutes
Now in this 360 minutes 15 % of the time loses so it is around 54 minutes loses daily . Hence effectively workers 304 minutes per day for the work .
Now on average on worker can done 304/40 = 7.6 orders a day . Make this 7 orders per day as half of the order dont make it any sense.
Now daily 125 routine a day . 1 workers can do 7 orders maximum per day .